The honest read

Building in Jackson Hole.

Jackson, Wilson, Teton Village and the county: who reviews your house, what the land asks of it, and what I'd check before you buy.

Jackson is the hardest place in the region to build a house. Most of the hard part comes before anyone draws it.

The fire class, the habitat tier, the size of the house and the season you can dig are settled first. Know them going in, and the design moves faster.

I spent six years on the Jackson Town Planning Commission, including as chair. I've sat on the side of the table that applies these rules.

I've worked with the Town's Planning & Building Department, the County's Planning & Building Services, Jackson Hole Fire/EMS and County Engineering myself. For this guide I've gone by each office's current documents, checked 16 November 2026. I check them again every spring.

The first question on any parcel

Town or county: who reviews your house

The Town of Jackson is the only incorporated town in Jackson Hole and runs its own review. Wilson, Teton Village, Moose, Kelly, Moran, Hoback and the land between are unincorporated Teton County. Both work from the 2024 codes, and since 1 January 2025 every private parcel in both sits inside the mapped wildland-urban interface.

Who reviews a single-family house in Jackson Hole, by place
Where the lot isWho reviews the houseWhat comes firstReview time
The Town of JacksonThe Town's Planning & Building Department, which checks the zoning inside the building permit.A wildfire permit from Jackson Hole Fire/EMS.Not published.
Unincorporated Teton CountyTeton County Planning & Building Services, with County Engineering for septic, grading and floodplain.The Fire Marshal's wildfire review, then the Natural Resources Assessment.Not published.
Teton Village and the other planned resortsTeton County, which approves nothing inconsistent with the resort's master plan, and the resort's own design review.The Fire Marshal's wildfire review. A lot on an approved master plan skips the Natural Resources Assessment.Not published.

Neither office publishes a review time for a house. What they do publish is the order, and in Jackson the order is most of the schedule.

Alta is on the Idaho side of the Tetons but in Teton County, Wyoming. It builds by the County's rules, owes a quarter of the workforce housing requirement, and is inspected on Wednesdays.

Private land inside Grand Teton National Park, around Moose, Kelly and Moran, is still Teton County: the County zones it and issues the permits. The Park's say is over access. A drive or utility line across park land takes a Park special use permit and federal environmental and historic review.

Residential permits

Office by office

For a single-family house. Commercial work and subdivisions follow other rules in both offices.

The Town of Jackson

  • A house in the NL and NM zones needs a building permit and nothing more: no design review, no Planning Commission, no Town Council.
  • It becomes a discretionary review when the lot's average cross-slope is 10% or more (a Hillside Conditional Use Permit, unless the lot was platted before 9 November 1994), when it sits in the Natural Resources Overlay (an Environmental Analysis), when it is in a flood hazard area, or when you add an accessory unit (a Basic Use Permit).
  • The wildfire permit number from Jackson Hole Fire/EMS goes on the application. The application goes to the Building Division as PDFs by email; the Town takes no paper and issues nothing over the counter.
  • In NL-2, the front setback is 25 ft, the sides 15 ft and the rear 25 ft, with a floor area ratio of .40 and at least 60% of the lot in landscape. In NL-3 and NL-4, 20 ft, 10 ft and 25 ft, with .40 and 45%.
  • Two stories, and the height limit rises with the roof: 26 ft at 3/12 or flatter, 28 ft at 4/12 or 5/12, 30 ft at 6/12 or steeper.
  • A detached house is capped at 8,000 sf habitable, basement excluded. Any house of 5,000 sf or more is sprinklered.
  • The 2024 residential, building, fire and wildland-urban interface codes and the 2021 energy code. Ground snow load 93 psf and frost depth 34 in, with no frost-protected shallow foundations. No wood shakes, shingles or wood siding, and propane tanks go underground.
  • Every house connects to Town water and sewer, and the capacity fees are paid before the permit. For three bedrooms, water is $1,564 plus $451 for each 1,000 sf of irrigated landscape, and sewer is $5,623. Each bedroom beyond three adds $390 and $1,407.
  • No digging in a Town street from 15 October to 15 April, and none in a street for 5 years after it is paved. Plan the service connection for summer.
  • Outdoor light no warmer than 3000 K, fully shielded over 600 lumens. Landscape lighting is solar powered.

From the Town's Land Development Regulations as updated 29 October 2026, its Municipal Code of 25 September 2026, its One and Two Family Building Permit Application of June 2026, and its Building and Design Criteria pages.

Unincorporated Teton County

  • Two reviews come before the County takes the submittal. Jackson Hole Fire/EMS reviews the site for wildfire and sets its ignition-resistant class, in 7 to 10 working days. Then the Natural Resources Assessment, at the level the overlay map sets for the lot.
  • Then the building permit, through the County's online portal in a submittal week booked with the permit tech. Planning checks the zoning inside it. One house on an existing lot needs no sketch plan, development plan or use permit.
  • Every house is engineered by a civil or structural engineer licensed in Wyoming, with stamped structural drawings and calculations beside the architect's stamped set.
  • The 2024 codes and the 2021 energy code. Glass is held to 30% of the wall above grade unless an energy calculation shows the house still complies, and a third party tests it for air leakage before you move in.
  • Snow load is read for the site from the ASCE Hazard Tool; the County no longer publishes a map. Frost depth is 34 in.
  • Sprinklers from 5,000 sf, and covered decks, porches and porte-cocheres count toward it.
  • In R-1 and R-2, the house sits 50 ft from a public road and 30 ft from a private road and the other lines. In R-3, 25 ft from the street and 10 ft from the sides and rear. Height 30 ft at any point and 37.5 ft overall.
  • A house is capped at 8,000 sf habitable, basement excluded, and any one building at 10,000 sf. Floor area on the lot is 10,000 sf at most in R-3 and on smaller R-1 and R-2 lots; larger parcels earn more by formula, and more than that takes the Floor Area Option, on 35 acres or more.
  • Earth tones and non-reflective exteriors. Fencing built so wildlife can cross it. Bear-resistant trash, on the construction site too.
  • Since 1 July 2026, every outdoor fixture is fully shielded and no warmer than 3000 K, within 0.5 lumens per sf of site development in the rural zones. String lights only from 25 October to 15 January.
  • Above 2,500 sf of conditioned space, an Energy Mitigation fee that rises with size, with separate charges for snowmelt, pools and extra fireplaces, and credits back for solar and ground-source heat.

From the County's 2025 Building Codes Resolution, effective 1 July 2025, its 2024 Fire Code Resolution and wildfire guidance, its residential submittal requirements, its Land Development Regulations, the lighting amendment effective 1 July 2026, and its 2026 fee schedule.

Teton Village and the planned resorts

  • Teton Village, the Jackson Hole Golf and Tennis Club and Snake River Canyon Ranch are planned resorts. Each follows its own master plan, and the County approves nothing inconsistent with it.
  • The County still issues the building permit, and the wildfire review still comes first. A lot on an approved master plan skips the Natural Resources Assessment.
  • In the original Teton Village, the Teton Village Architectural Committee reviews the house under the 1997 covenants and the master plan's design guidelines. Submittals are due two weeks before its monthly meeting. Granite Ridge and Shooting Star have their own associations.
  • Water and sewer come from the Teton Village Water and Sewer District. Connection is required, and the district's permit and its Board's approval come before construction, with fees set by the plumbing fixtures in the house.

From the County's Land Development Regulations as updated 1 July 2026, the Teton Village Architectural Committee's published process, and the Teton Village Water and Sewer District's rules of 9 September 2015.

What I look at

The land, the water and the build

Wildfire

The fire review gives every lot a class. IR1, the strictest, takes sprinklers in any new house, a Class A roof, ignition-resistant walls and decks, tempered glass and ember-resistant vents. The class shapes the design, so I apply for it early.

In the County, a driveway is required when the house sits more than 150 ft from a fire access road. It is 12 ft wide, with a turnaround past 150 ft and turnouts past 200 ft where it is narrower than 20 ft. A drive that climbs more than 10% for any length can require sprinklers.

Habitat and water

The County's overlay map puts every lot in a tier. Base is a desktop checklist. Mid is an Environmental Review with a site visit by a biologist. High is a full Environmental Analysis. In Mid and High, the house goes on the part of the lot with the least habitat value. In a subdivision the County approved, a lot of 2 acres or less, or one with an approved building envelope, stays at the checklist.

Buildings stay 150 ft from the Snake, Gros Ventre, Hoback and Buffalo Fork, 100 ft from streams and natural ponds, 50 ft from wetlands and 15 ft from ditches, and well back from swan habitat and eagle nests. In Town, Flat Creek takes 25 to 50 ft and wetlands 30 ft.

Skylines and foregrounds
The Scenic Resources Overlay covers the skylines and foregrounds seen from the state highways, Spring Gulch Road, South Park Loop Road and the Alta road. Nothing may break the skyline. Where there is no other place for the house, it stands no more than 20 ft above original grade, and the application carries a visual simulation.
Septic and wells

The County's septic rules are stricter than the state's: 4 ft of soil between the field and the high groundwater, designed by an engineer, with a test pit and three percolation tests. Plan on about 2 acres for a field and its full replacement, 100 ft from any well, the neighbors' included. Within 500 ft of public sewer, you connect.

No new systems go in from 15 November to 15 April. A lot that looks dry in September can fail in June: the County will permit on assumed worst-case groundwater, or you can monitor through the spring high. A well needs a State Engineer permit before it is drilled, usually 1 to 2 weeks.

Outside Town, Wilson connects to sewer through the Town of Jackson's permit and its capacity fees. The Aspens, Hoback Junction and Indian Paintbrush have their own districts: ask the district before you plan on a connection.

Slope and flood
No building on natural slopes over 25% in Town or over 30% in the County, and a geotechnical report for grading on the steep ones. In a Town flood zone, the lowest floor, basement included, sits 1 ft above base flood, and nothing is built in the floodway. In the County, the County Engineer issues the floodplain permit.
Workforce housing
Every new house in Town owes workforce housing mitigation, and so does every house in the County over 3,000 sf. A vacant lot carries no credit. The requirement grows faster than the house: by the formula, an 8,000 sf house owes more than four times what a 2,500 sf one does. Short of a whole unit, it is paid as a fee before the permit, set each year by resolution. Ask for the current figure before you settle on a size.
Covenants and associations
The Town and the County enforce their codes, not your covenants, and the covenants can be stricter. Get the association's approval in writing before construction. If you're buying a lot, read the CC&Rs before you close, or have me review them and tell you whether they fit how you mean to use the house.

Before you buy in Jackson Hole

Eight questions to ask before you buy here

  1. Is the lot in the Town or the county? In a planned resort, which master plan governs it?
  2. What tier does the Natural Resources Overlay map give the lot, and is it in the Scenic Resources Overlay?
  3. What ignition-resistant class is it likely to draw, and how long and how steep is the drive?
  4. How big can the house be here, and how big do you want it? From 5,000 sf it is sprinklered. Past 8,000 sf habitable, it isn't allowed.
  5. Is there public sewer within 500 ft, or will it be septic? How high does the groundwater come in spring?
  6. Is a river, stream, wetland or ditch close enough for its setback to move the house?
  7. What will workforce housing mitigation cost at the size you want?
  8. Is there an association, and what does its design review require?

The twenty questions for any lot

Twenty years of designing houses for how people live in the mountains.

That experience makes the process shorter and the decisions clearer.

I do Feasibility Studies in the Town of Jackson and across Teton County. An Overview is $1,500 and takes five business days: the zoning that applies, the overlays named, and a site plan with the setbacks drawn.

See the Feasibility Study

Building in Teton Valley

Building in Star Valley

John C. Stennis, Architect, Alpine, Wyoming. Checked 16 November 2026 against each office's current documents, and again every spring. Rules change; confirm with the office before you submit.